St. Mirren Football Club

New Stadium

Greenhill Road, Paisley

Case Studies

Pass your mouse over each stage in the development to see the progress photos...

2008

  • January - A blank canvas - Barr take possession of the site
  • Early February - Site clearance completed, installation of the foundations
  • Mid February - The first steelwork is erected at the East Stand
  • Late February / Early March - Installation of the precast tarracing decks
  • Mid March - Installation of the East Stand Floors
  • Early April - The stadium begins to take shape
  • Mid April - Blockwork commences on the East Stand
  • May - Pitch preparation commences
  • June - External envelope nears completion
  • July - The pitch begins to take shape